Back to projects

Water Treatment and Distribution Upgrade

Campbelltown, Ontario

completeDrinking WaterSCF
Federal contribution
$1.8M
$1,800,000
Federal share33%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
2017201920212023
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Hiawatha First Nation
Construction start
Apr 2, 2021(actual)
Construction end
May 31, 2023(actual)

Against the original forecast

  • Construction start8 months lateforecast Jul 20, 2020
  • Construction end14 months lateforecast Mar 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46847 in the federal list. How to read these figures.