Highway 11 Reconstruction Project - Phase 2
Federal contribution
$1.5M
$1,536,326
Federal share27%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
201720182019
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Kapuskasing
- Construction start
- Jul 16, 2018(actual)
- Construction end
- Nov 11, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast May 14, 2018
- Construction end3 weeks earlyforecast Nov 29, 2019
Also in Kapuskasing
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46850 in the federal list. How to read these figures.