Frenchman's Head Sewage Treatment Plant and Collection System
Federal contribution
$1.8M
$1,833,333
Federal share33%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
2017201920212023
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Lac Seul First Nation
- Construction start
- Jun 30, 2021(actual)
- Construction end
- Mar 8, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 5, 2021
- Construction end12 months lateforecast Mar 22, 2023