Burwash Water Treatment Plant

Burwash Landing, Yukon

completeDrinking WaterSCF
Federal contribution
$3.9M
$3,870,000
Federal share75%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2016
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Kluane First Nations
Construction start
May 24, 2019(actual)
Construction end
Oct 13, 2020(actual)

Against the original forecast

  • Construction start11 months lateforecast Jun 30, 2018
  • Construction end10 months earlyforecast Jul 31, 2021

Also in Burwash Landing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46863 in the federal list. How to read these figures.