Burwash Water Treatment Plant
Federal contribution
$3.9M
$3,870,000
Federal share75%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2016
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Kluane First Nations
- Construction start
- May 24, 2019(actual)
- Construction end
- Oct 13, 2020(actual)
Against the original forecast
- Construction start11 months lateforecast Jun 30, 2018
- Construction end10 months earlyforecast Jul 31, 2021
Also in Burwash Landing
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46863 in the federal list. How to read these figures.