Rehabilitation of Various Bridges on the highway system throughout the Northwest Territories
Hay River, Northwest Territories
Federal contribution
$33.6M
$33,562,500
Federal share75%
of $44.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
today
2017202020232026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Jul 1, 2016(actual)
- Construction end
- Sep 30, 2027(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46882 in the federal list. How to read these figures.