Highway Structures and Access Road Improvements Bundle
Federal contribution
$19.1M
$19,050,000
Federal share75%
of $25.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
today
20162019202220252028
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Government of Northwest Territories
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Sep 30, 2027(forecast)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 1, 2016
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46884 in the federal list. How to read these figures.