Highway No. 2 Rehabilitation Work

Moose Jaw, Saskatchewan

completeHighways and RoadsNRP
Federal contribution
$2.7M
$2,674,000
Federal share48%

of $5.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Province of Saskatchewan
Construction start
May 28, 2018(actual)
Construction end
Oct 17, 2018(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Sep 28, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47107 in the federal list. How to read these figures.