Hamlet of Fort Liard Sewage Lagoon Upgrade

Fort Liard, Northwest Territories

completeWastewaterSCF
Federal contribution
$135,160
Federal share9%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 8, 2016
2017201820192020
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Hamlet of Fort Liard
Construction start
Sep 25, 2017(actual)
Construction end
Aug 31, 2020(actual)

Against the original forecast

  • Construction start13 months lateforecast Sep 1, 2016
  • Construction end8 months lateforecast Dec 31, 2019