Highway No. 11 Rehabilitation Work
Federal contribution
$15.2M
$15,200,000
Federal share50%
of $30.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172019202120232025
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end4 weeks lateforecast Nov 30, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47167 in the federal list. How to read these figures.