Highway No. 1 Rehabilitation Work

Gull Lake, Saskatchewan

completeHighways and RoadsNRP
Federal contribution
$3.9M
$3,920,000
Federal share50%

of $7.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20172019202120232025
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Province of Saskatchewan
Construction start
Jun 8, 2019(actual)
Construction end
Jul 6, 2025(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2019
  • Construction end5 months earlyforecast Nov 30, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47168 in the federal list. How to read these figures.