Bus Rapid Transit Study
Federal contribution
$99,585
Federal share50%
of $199.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Sep 1, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2017
- Construction end4 months earlyforecast Dec 31, 2018
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47177 in the federal list. How to read these figures.