Back to projects

Bus Stop Accessibility

Halifax, Nova Scotia

completePublic TransitPTIF
Federal contribution
$123,492
Federal share49%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
20172018
Built
Program
Public Transit Infrastructure Fund
Construction start
Sep 1, 2016(actual)
Construction end
Feb 6, 2018(actual)

Against the original forecast

  • Construction end8 weeks earlyforecast Mar 31, 2018

Also in Halifax