Back to projects

Conventional Bus and MetroX Bus Expansion

Halifax, Nova Scotia

completePublic TransitPTIF
Federal contribution
$14.6M
$14,646,418
Federal share50%

of $29.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Public Transit Infrastructure Fund
Construction start
Dec 1, 2016(actual)
Construction end
Mar 1, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Sep 1, 2016
  • Construction end2 months lateforecast Dec 31, 2018

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47181 in the federal list. How to read these figures.