Halifax Ferry Terminal Upgrade

Halifax, Nova Scotia

completePublic TransitPTIF
Federal contribution
$493,013
Federal share49%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Public Transit Infrastructure Fund
Construction start
Mar 27, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 2, 2017