Transit Priority Measures Implementation- Phase 1

Halifax, Nova Scotia

completePublic TransitPTIF
Federal contribution
$200,000
Federal share50%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 16, 2016
201720182019
Built
Program
Public Transit Infrastructure Fund
Construction start
Sep 1, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 1, 2016
  • Construction end12 months earlyforecast Mar 31, 2020

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47189 in the federal list. How to read these figures.