Transit Priority Measures Implementation - Phase 2
Federal contribution
$450,000
Federal share50%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction end3 months earlyforecast Mar 31, 2020