Transit Security
Federal contribution
$1.5M
$1,506,470
Federal share50%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
201720182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Jun 28, 2019(actual)