Expansion of main entryway of the recreation centre in Saint-Ubalde

Saint-Ubalde, Quebec

completeRecreationSCF
Federal contribution
$73,745
Federal share33%

of $221.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2017
2017201820192020
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 1, 2018(actual)
Construction end
Mar 5, 2020(actual)

Against the original forecast

  • Construction start17 months lateforecast Nov 1, 2016
  • Construction end3.2 years lateforecast Dec 23, 2016

Also in Saint-Ubalde

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47724 in the federal list. How to read these figures.