Sandy Lake Water Treatment Plant
Federal contribution
$1.7M
$1,711,990
Federal share33%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 16, 2017
20182019
Built
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Municipal District of Opportunity No. 17
- Construction start
- Apr 9, 2018(actual)
- Construction end
- May 8, 2019(actual)
Against the original forecast
- Construction start3 weeks lateforecast Mar 16, 2018
- Construction end8 weeks earlyforecast Jun 30, 2019