Installation of elevating device for handicapped individuals in Saint-Jean-de-Dieu
Federal contribution
$35,721
Federal share33%
of $107.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
20172018
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Jean-de-Dieu
- Construction start
- Nov 27, 2017(actual)
- Construction end
- Jul 20, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Aug 7, 2017
- Construction end8 months lateforecast Nov 6, 2017