Back to projects

Construction of a tennis court in Saint-Maurice

Saint-Maurice, Quebec

completeRecreationSCF
Federal contribution
$82,864
Federal share33%

of $248.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
20172018
Built

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 1, 2017(actual)
Construction end
Sep 25, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 4, 2017
  • Construction end12 months lateforecast Sep 29, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47740 in the federal list. How to read these figures.