Construction of a tennis court in Saint-Maurice
Federal contribution
$82,864
Federal share33%
of $248.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2017
20172018
Built
Approved 8 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Parish Municipality of Saint-Maurice
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Sep 25, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 4, 2017
- Construction end12 months lateforecast Sep 29, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47740 in the federal list. How to read these figures.