Construction of an Aquatic Centre

Saint-Constant, Quebec

completeRecreationSCF
Federal contribution
$4.2M
$4,177,619
Federal share33%

of $12.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 8, 2017
20172018201920202021
Built

Approved 6 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Saint-Constant
Construction start
Oct 25, 2018(actual)
Construction end
Feb 15, 2021(actual)

Against the original forecast

  • Construction start6 months earlyforecast May 1, 2019
  • Construction end6 months lateforecast Aug 31, 2020