Back to projects

Reconstruction and renovation of the Parc olympique swimming pool and chalet in Pincourt

Pincourt, Quebec

completeRecreationSCF
Federal contribution
$431,393
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 22, 2018
20172018201920202021
Built

Approved 18 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Pincourt
Construction start
Aug 31, 2018(actual)
Construction end
Mar 31, 2021(actual)

Also in Pincourt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47748 in the federal list. How to read these figures.