Construction of a Multipurpose Outdoor Skating Rink

Saint-Aimé-du-Lac-des-Îles, Quebec

completeRecreationSCF
Federal contribution
$85,225
Federal share33%

of $255.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2017
20172018
Built

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 4, 2017(actual)
Construction end
May 15, 2018(actual)

Against the original forecast

  • Construction end6 months lateforecast Oct 31, 2017

Also in Saint-Aimé-du-Lac-des-Îles

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47749 in the federal list. How to read these figures.