Renovation of the Centre sportif Clément Tremblay in Chandler
Federal contribution
$842,859
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
2017201820192020
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Chandler
- Construction start
- Apr 3, 2018(actual)
- Construction end
- Dec 20, 2019(actual)
Against the original forecast
- Construction start8 weeks earlyforecast May 28, 2018
- Construction end14 months lateforecast Oct 15, 2018
Also in Chandler
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47752 in the federal list. How to read these figures.