Back to projects

Renovation of the Centre sportif Clément Tremblay in Chandler

Chandler, Quebec

completeRecreationSCF
Federal contribution
$842,859
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
2017201820192020
Built

Approved 6 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Chandler
Construction start
Apr 3, 2018(actual)
Construction end
Dec 20, 2019(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast May 28, 2018
  • Construction end14 months lateforecast Oct 15, 2018

Also in Chandler

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47752 in the federal list. How to read these figures.