Construction of an Aqua-Gym Complex in Dolbeau-Mistassini

Dolbeau-Mistassini, Quebec

completeRecreationSCF
Federal contribution
$4.4M
$4,400,000
Federal share33%

of $13.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201920212023
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Dolbeau-Mistassini
Construction start
Mar 1, 2019(actual)
Construction end
Jun 26, 2023(actual)

Against the original forecast

  • Construction start9 months lateforecast May 21, 2018
  • Construction end3.9 years lateforecast Jul 19, 2019