Acquisition of tire changer and balancer to enhance fleet maintenance

Renfrew, Ontario

completePublic TransitPTIF
Federal contribution
$2,707
Federal share27%

of $10.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 10, 2017
20172018
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Renfrew
Construction start
Mar 1, 2018(actual)
Construction end
Apr 30, 2018(actual)

Against the original forecast

  • Construction start6 months earlyforecast Sep 1, 2018
  • Construction end8 months earlyforecast Dec 31, 2018