Install Wi-Fi and GPS services to our four buses to improve service reliability.
Federal contribution
$2,500
Federal share50%
of $5.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
2017
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Township of Russell
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Aug 1, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2017
- Construction end8 months earlyforecast Mar 30, 2018
Also in Russell
- Upgrades to the Water Distribution System$4.5M
- Watermain Twinning and Water and Wastewater Servicing of Russell's Commercial Park$787.3K
- Reconstruction and Surface Treatment - Route 200$326.8K
- Rehabilitation of Embrun Bowling Hall Equipment$115.9K
- Purchase of hybrid vehicles to support an existing transit service for rural regions surrounding City of Ottawa, Ontario$75.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47799 in the federal list. How to read these figures.