Resurfacing of the park and ride
Federal contribution
$40,446
Federal share50%
of $80.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedFeb 10, 2017
ApprovedJul 10, 2017
Built
Approved 5 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Township of Russell
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 30, 2018
Also in Russell
- Upgrades to the Water Distribution System$4.5M
- Watermain Twinning and Water and Wastewater Servicing of Russell's Commercial Park$787.3K
- Reconstruction and Surface Treatment - Route 200$326.8K
- Rehabilitation of Embrun Bowling Hall Equipment$115.9K
- Purchase of hybrid vehicles to support an existing transit service for rural regions surrounding City of Ottawa, Ontario$75.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47801 in the federal list. How to read these figures.