Schedule

Announced and approvedMar 31, 2017
20172018
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Thorold
Construction start
Jul 1, 2017(actual)
Construction end
Nov 20, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end9 months lateforecast Mar 1, 2018