Installation of New Bus Laybys and Bus Selters at Seven Bus Stops
Federal contribution
$157,500
Federal share50%
of $315.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Thorold
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Nov 20, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end9 months lateforecast Mar 1, 2018