Installation of a new bus layby, 2 bus shelters and new sidewalk with a stopping complex on Towpath

Thorold, Ontario

completePublic TransitPTIF
Federal contribution
$214,008
Federal share50%

of $428.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201820192020
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Thorold
Construction start
Mar 1, 2018(actual)
Construction end
Nov 30, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Dec 1, 2017
  • Construction end4 weeks earlyforecast Dec 31, 2019