Installation of 10 new concrete pads with accessible markings at multiple bus locations for improved accessibility at bus stops
Federal contribution
$46,000
Federal share50%
of $92.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
201720182019
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Thorold
- Construction start
- Oct 15, 2017(actual)
- Construction end
- Apr 30, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 1, 2017
- Construction end18 months lateforecast Nov 1, 2017