Back to projects

Installation of 10 new concrete pads with accessible markings at multiple bus locations for improved accessibility at bus stops

Thorold, Ontario

completePublic TransitPTIF
Federal contribution
$46,000
Federal share50%

of $92.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
201720182019
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Thorold
Construction start
Oct 15, 2017(actual)
Construction end
Apr 30, 2019(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Oct 1, 2017
  • Construction end18 months lateforecast Nov 1, 2017

Also in Thorold

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47908 in the federal list. How to read these figures.