Remediation of Transit Parking Lot at Transit Terminal to improve accessibility

Thorold, Ontario

completePublic TransitPTIF
Federal contribution
$75,000
Federal share50%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
201720182019
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Thorold
Construction start
Mar 1, 2018(actual)
Construction end
May 31, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Feb 1, 2018
  • Construction end7 months earlyforecast Dec 31, 2019