2018 Replacement Bus Procurement: Replacement of 3 conventional transit buses (3 x 12m/40ft buses)

Kingston, Ontario

completePublic TransitPTIF
Federal contribution
$738,863
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedFeb 10, 2017
ApprovedNov 8, 2017
20172018
Built

Approved 9 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Kingston
Construction start
Jan 1, 2017(actual)
Construction end
Jan 30, 2018(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 31, 2017