2017 Hoist Installation
Federal contribution
$89,000
Federal share50%
of $178.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
20172018
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Kingston
- Construction start
- Aug 14, 2017(actual)
- Construction end
- Feb 23, 2018(actual)
Against the original forecast
- Construction start7 months lateforecast Jan 1, 2017
- Construction end5 weeks earlyforecast Mar 31, 2018
Also in Kingston
- City of Kingston Third Crossing Bridge$60.0M
- Ministry of Transportation Ontario Eastern Region New Ferry Vessels$31.3M
- Kingston Wastewater Treatment Plant Upgrades$25.0M
- Isabel Bader Centre for the Performing Arts at Queen's University at Kingston$15.0M
- Long Range Battery Electric Conventional Transit Buses and Bio- Diesel/Hybrid Buses$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47945 in the federal list. How to read these figures.