2017-2018 Bus Stop Infrastructure Upgrades and Shelter Installation at multiple bus stops

Kingston, Ontario

completePublic TransitPTIF
Federal contribution
$382,725
Federal share50%

of $765.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 10, 2017
201720182019
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Kingston
Construction start
May 30, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2017

Also in Kingston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47949 in the federal list. How to read these figures.