Study for New Centralized Transit Terminal & Route Network Implementation (Phase I)
Federal contribution
$149,791
Federal share50%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 16, 2017
ApprovedJul 10, 2017
2017201820192020
Built
Approved 6 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Thunder Bay
- Construction start
- Aug 17, 2017(actual)
- Construction end
- Mar 30, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017
- Construction end6 months lateforecast Oct 1, 2019
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47960 in the federal list. How to read these figures.