Accessible Bus Stop Improvements & Shelter Upgrades at multiple bus stops
Federal contribution
$164,255
Federal share48%
of $340.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 16, 2017
ApprovedJul 10, 2017
201720182019
Built
Approved 6 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Thunder Bay
- Construction start
- Jun 2, 2017(actual)
- Construction end
- Jul 23, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2017
- Construction end4 months lateforecast Mar 31, 2019
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47961 in the federal list. How to read these figures.