Replacement/Updating of Bus Stop Signage and Route Wayfinding Signage
Federal contribution
$60,000
Federal share50%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
201720182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Thunder Bay
- Construction start
- Apr 7, 2017(actual)
- Construction end
- May 10, 2019(actual)
Against the original forecast
- Construction end6 weeks lateforecast Mar 31, 2019