Transit Facility Capital - Parking Lot /Lighting/ Building upgrades
Federal contribution
$314,000
Federal share50%
of $628.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 16, 2017
2017201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Thunder Bay
- Construction start
- Jul 20, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2017
- Construction end9 months lateforecast Mar 31, 2019
Also in Thunder Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47965 in the federal list. How to read these figures.