Replacement of Transit Bus Hoist

Thunder Bay, Ontario

completePublic TransitPTIF
Federal contribution
$110,000
Federal share50%

of $220.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
20172018
Built
Program
Public Transit Infrastructure Fund
Construction start
May 26, 2017(actual)
Construction end
Jan 31, 2018(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 1, 2017
  • Construction end8 weeks earlyforecast Mar 31, 2018