Windsor Street Active Living Corridor - Sidewalk Connection

Thunder Bay, Ontario

completePublic TransitPTIF
Federal contribution
$103,250
Federal share50%

of $206.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
20172018
Built
Program
Public Transit Infrastructure Fund
Construction start
Sep 11, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end2 months lateforecast Jun 30, 2018