Construction of Pedestrian Crossover

Thunder Bay, Ontario

completePublic TransitPTIF
Federal contribution
$48,044
Federal share48%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
2017
Built
Program
Public Transit Infrastructure Fund
Construction start
Jul 23, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2017

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47972 in the federal list. How to read these figures.