Pedestrian Wayfinding Signage

Thunder Bay, Ontario

completePublic TransitPTIF
Federal contribution
$100,000
Federal share50%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
201720182019
Built
Program
Public Transit Infrastructure Fund
Construction start
Aug 21, 2017(actual)
Construction end
Dec 10, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end4 months earlyforecast Mar 31, 2019

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47974 in the federal list. How to read these figures.