Construction of New Bike Lane

Thunder Bay, Ontario

completeActive TransportationPTIF
Federal contribution
$55,000
Federal share50%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
20172018
Built
Program
Public Transit Infrastructure Fund
Construction start
May 17, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 1, 2017
  • Construction end15 months earlyforecast Mar 31, 2019