Back to projects

Installation of New Bike Racks for Business

Thunder Bay, Ontario

completeActive TransportationPTIF
Federal contribution
$10,000
Federal share50%

of $20.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2017
20172018
Built
Program
Public Transit Infrastructure Fund
Construction start
Feb 23, 2017(actual)
Construction end
Jan 31, 2018(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Apr 1, 2017
  • Construction end8 weeks earlyforecast Mar 31, 2018

Also in Thunder Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47977 in the federal list. How to read these figures.