Back to projects

Downtown Transit Terminal Renovations

Brantford, Ontario

completePublic TransitPTIF
Federal contribution
$300,000
Federal share50%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Brantford
Construction start
Sep 7, 2017(actual)
Construction end
Feb 16, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Jan 1, 2017
  • Construction end6 weeks earlyforecast Mar 31, 2018

Also in Brantford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48066 in the federal list. How to read these figures.