Market Parkade Rehabilitation and Repairs

Brantford, Ontario

completePublic TransitPTIF
Federal contribution
$2.1M
$2,150,000
Federal share50%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Brantford
Construction start
Nov 1, 2017(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start10 months lateforecast Jan 1, 2017

Also in Brantford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48067 in the federal list. How to read these figures.