Back to projects

Resolute Bay Water System Upgrade

Resolute Bay, Nunavut

completeDrinking WaterSCF
Federal contribution
$12.8M
$12,804,086
Federal share64%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 3, 2017
20172019202120232025
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 11, 2019(actual)
Construction end
Feb 7, 2025(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 1, 2019
  • Construction end10 months lateforecast Mar 31, 2024

Also in Resolute Bay