Resolute Bay Water System Upgrade
Federal contribution
$12.8M
$12,804,086
Federal share64%
of $20.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 3, 2017
20172019202120232025
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Nunavut Ministry of Community and Government Services
- Construction start
- Apr 11, 2019(actual)
- Construction end
- Feb 7, 2025(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 1, 2019
- Construction end10 months lateforecast Mar 31, 2024
Also in Resolute Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48346 in the federal list. How to read these figures.