Back to projects

Second Marine Berth

Cape Breton, Nova Scotia

completeTourismSCF
Federal contribution
$6.7M
$6,658,262
Federal share33%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 23, 2017
20172018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 15, 2018(actual)
Construction end
Jan 20, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2018
  • Construction end2 months earlyforecast Mar 31, 2021

Also in Cape Breton